Whitlam Stage 3: tip of the iceberg

Another tender has opened for works lying between Whitlam Stage 3 and Namarag. Moving power lines will the Suburban Land Agency busy.

The 11 kV power line over Whitlam Stage 3 is going to be put underground. The 11 kV relocation is only a small project. Keep in mind, that until overhead power lines have been moved outside the estate project area, that the Suburban Land Agency cannot begin construction work.

A much bigger project is the 330 kV power line over the north side of the Molonglo River opposite Coombs. This will also be put underground along William Hovell Drive. To my knowledge there has been no tender for this yet, but it will certainly be coming.

It does not seem the estates of Molonglo State 3 East are close to start just yet.

SLA MVIS 11kVa Relocation Project, tender SL210078
Tender documents. SLA MVIS 11kVa Relocation Project, tender SL210078, accessed 22 March 2021.
Moving an 11 kV power line COMBINED_2803_SITE3_MVIS_11KV_WVR003_IFT_20210304. SLA MVIS 11kVa Relocation Project, tender SL210078
Moving an 11 kV power line COMBINED_2803_SITE3_MVIS_11KV_WVR003_IFT_20210304. SLA MVIS 11kVa Relocation Project, tender SL210078

Molonglo Valley Interceptor Sewer Odour Mitigation Project

Mentioned last week at the Molonglo Valley Community Forum, this is another project that needs their attention. The Molonglo Valley sewer pipe needs to be tamed.

Molonglo Valley Interceptor Sewer Odour Mitigation Project
Molonglo Valley Interceptor Sewer Odour Mitigation Project

Leave a Comment

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s