18 years later and still not built!

We must remain sceptical of consultations. The consultation for (ACT) Ten Year Master Plan Trunk Cycling and Walking Path Infrastructure 2004, shows us that the recommendations have still not be implemented 18 years later. The process in 2004 has an eerie familiarity to the 2021 District Planning consultations.

Create a place for people in Belconnen

An effort to make the heart of Belconnen Town Centre better for people with parks, facilities and pedestrian and cycle paths. The report’s name is misleading, but the idea is great, particularly for Belconnen cyclists.

Belconnen Town Centre consultation 2020

Changes to the Belconnen Town Centre are afoot. The urban planning review for Belconnen foreshores started in December 2020. The urban space around Westfield will be made a nicer place for people – creating place. Further information on YourSay. Getting good bike paths past Westfield in Belconnen have to be a priority.

Belconnen Bikeway during construction

The Belconnen Bikeway has come a long way but was not finished before the 2020 ACT Election, despite having been promised at the election four years before that. Your guide to cycling in Canberra TCCS map (January 2019) shows that the bikeway had been expected to be finished well before the election.

Belconnen Bikeway: finished in part

The construction of the Belconnen Bikeway started last year and some progress has been made. The separated bike and pedestrian paths along the old bus road are finished but not open. Construction has started on Emu Bank. The section through the University of Canberra is largely finished.